Residential
Installations – water meters
·
We are 65 - 70 percent finished
with installations south of Holloway, west of Century Ave., east of White Bear
Ave., and north of Conway.
·
Installation are 45 percent
complete in an area bordered approximately by I-94 in the south, Arlington in
the north, McKnight in the East, and Burlington in the west.
·
Mailings have gone out to property
owners in Maplewood and Saint Paul, south of I-94 and bordering either side of
McKnight road down to the southern edge of both cities. The area extends to the
railroads in the west and the Century Avenue in the east.
Commercial
Installations
·
We are nearly finished with the
installation of large (1.5- and 2-inch) residential and commercial meters.
·
We have begun installing
commercial meters 3-inches and larger, with 44 of these large meters replaced.
These larger meters are more involved and require a longer installation period.
This affects the length of time the water service will be interrupted.
Businesses should plan accordingly when setting appointments.
·
Complaints continue to decline and
remain low relative to the number of meters installed at about 1 percent
overall, with leaks being the number one complaint.
Please be aware that
in a minority of cases, in which repeated attempts to contact the homeowner or
resident have gone without response for at least two months, we have
disconnected water services until we can arrange to have a new meter installed.